PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4

PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.

Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s)
A 5 3 $1,000 $1,800 -
B 6 5 $400 $550 -
C 6 5 $400 $575 -
D 3 2 $750 $900 A
E 5 3 $1,350 $2,250 C
F 6 3 $900 $1,800 B

What is the duration of the project (in weeks)?

What is the target duration of the project (after crashing the project)?

By how many weeks should activity A be crashed?

By how many weeks should activity B be crashed?

By how many weeks should activity C be crashed?

By how many weeks should activity D be crashed?

By how many weeks should activity E be crashed?

By how many weeks should activity F be crashed?

What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Public Finance An International Perspective

Authors: Joshua E. Greene

1st Edition

9814365041, 978-9814365048

More Books

Students also viewed these Finance questions

Question

Understand the different approaches to job design. page 167

Answered: 1 week ago