pman 635 final exam What is the duration (length of critical path) of the project which has the following activity-predecessor-duration table: Activity Prodecessors Duration A.
pman 635 final exam What is the duration (length of critical path) of the project which has the following activity-predecessor-duration table:
Activity Prodecessors Duration
A. Start 9
B Start 6
C Start 3
D A. 11
E b, c 7
F. c 9
G. D 12
H d,e,f 18
I. f 15