Popol Construction Company has entered into a contract beginning January 1, 2015, to build a parking complex. It has been estimated that the complex will
Popol Construction Company has entered into a contract beginning January 1, 2015, to build a parking complex. It has been estimated that the complex will cost $1,500,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $2,250,000. The following data pertain to the construction period.
2015 | 2016 | 2017 | |
Costs to date | $675,000 | $1,125,000 | $1,525,000 |
Estimated costs to complete | 825,000 | 375,000 | 0 |
Progress billings to date | 675,000 | 1,375,000 | 2,250,000 |
Cash collected to date | 600,000 | 1,250,000 | 2,250,000 |
Instructions
- Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
- Using the cost-recovery method, compute the estimated gross profit that would be recognized during each year of the construction period.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started