Question
Populace Manufacturing Inc., (the company) a pre-fab shack manufacturer, is considering bidding on a job. In order to submit this bid, the company needs to
Populace Manufacturing Inc., ("the company") a pre-fab shack manufacturer, is considering bidding on a job. In order to submit this bid, the company needs to calculate the total cost of performing this job. Financial details for the proposed job are as follows:
Number of inspections | 80 |
Number of machine hours | 600 |
Number of direct labour hours | 2,000 |
Direct materials | $21,000 |
Direct labour | $16,000 |
Number of material moves | 25 |
The company has three different categories of overhead. The overhead costs for each of the categories for the next year are as follows:
Costs | Cost Driver | Expected Activity | |
Materials handling | $30,000 | Material moves | 15,000 |
Maintenance | $360,000 | Machine hours | 24,000 |
Inspection | $14,000 | Inspections | 4,000 |
The company applies overhead using a predetermined overhead rate based upon a budgeted direct labour hours of 50,000.
Using the above information answer the following questions.
Question 38 (1 point)
Question 38 options:
If the company used activity-based costing, calculate the total overhead cost that would be assigned for material handling to the job
Question 39 (1 point)
Question 39 options:
If the company used activity-based costing, calculate the total overhead cost that would be assigned for maintenance to the job
Question 40 (1 point)
Question 40 options:
If the company used activity-based costing, calculate the total overhead cost that would be assigned for inspections to the job
Question 41 (1 point)
Question 41 options:
If the company used activity-based costing, calculate the total of material cost + direct labour cost that would be assigned to the job
Question 42 (1 point)
Question 42 options:
If the company used activity-based costing, calculate the total cost that would be assigned to the job
Question 43 (2 points)
Question 43 options:
If the company allocated overhead to the job using a plantwide overhead rate, calculate the total overhead cost assigned to the job
Question 44 (1 point)
Question 44 options:
If the company allocated overhead to the job using a plantwide overhead rate, calculate the total cost assigned to the job
Question 45 (1 point)
It would not be appropriate to adopt an ABC policy if which of the following were true:
Question 45 options:
|
| ||
|
| ||
|
| ||
|
|
Next Page
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started