Poucask Ltd are piloting a project to install broadband internet in residential properties on behalf of broadband providers. Each installation requires a visit from an engineer in a company van), for an average visit of 2 hours. Each installation requires one piece of hardware (router) and on average 10 metres of cable A contract has been agreed for 250 installations in May. Each installation will generate 250 of income for Poucas The total costs for running a van for one year is 20,000. This includes $10,000 of depreciation The cost of a router is 20, cable is per metre, and labour is 20 per hour. To deliver the contract, two engineers (each with their own van) will be needed. Assuming the project goes well, atender is being produced to do the same work for three years. The project details are: 1,250 Installations carried out each month Labour costs will be assumed to be the same as above and paid for in the same period as incurred Material costs will be assumed to be the same as above, however will be ordered and paid for once a year (first order year) The income will be 200 per installation The project will increase overheads by 500,000 per year. Payable in the same period as incurred. The project will require purchase of 10 new vans. The company have a choice Option 1 Electric Van Purchase price Running Costs Capital Allowance Residual value 70.000 2,500 per annum 100% on purchase 20.000 end of year 3 Option 2: Internal Combustion Engine Van Purchase price 50,000 Running Costs E 10.000 per annum Capital Allowance 15% per annum (reducing balance method) Residual Value 20,000 end of year 3 Capital allowances are deductible from profits for tax purposes. Tax is charged at 20% of profits, and payable in the following year. Company wide cost of capital is 20% Question One For the tender, select an appropriate management accounting tool to evaluate the data above, and present the implications of the two options. Include a justification of your approach, and a clear recommendation of which option to select. [note: your answer should show your workings and approach, and include a very brief explanation no more than a maximum of 300 words ] 50 Marks Question Two The company have never used all electric vehicles before and are uncertain about the estimated running costs. Estimates range from 1,000 to 5,000 pervan per annum. They are certain about the same estimates for option 2. To what extent does this uncertainty inform the decision to proceed with Option 1 or Option 2? note: your answer should show your workings and approach and include a very brief explanation ne more than maximum of 100 words ] Poucask Ltd are piloting a project to install broadband internet in residential properties on behalf of broadband providers. Each installation requires a visit from an engineer in a company van), for an average visit of 2 hours. Each installation requires one piece of hardware (router) and on average 10 metres of cable A contract has been agreed for 250 installations in May. Each installation will generate 250 of income for Poucas The total costs for running a van for one year is 20,000. This includes $10,000 of depreciation The cost of a router is 20, cable is per metre, and labour is 20 per hour. To deliver the contract, two engineers (each with their own van) will be needed. Assuming the project goes well, atender is being produced to do the same work for three years. The project details are: 1,250 Installations carried out each month Labour costs will be assumed to be the same as above and paid for in the same period as incurred Material costs will be assumed to be the same as above, however will be ordered and paid for once a year (first order year) The income will be 200 per installation The project will increase overheads by 500,000 per year. Payable in the same period as incurred. The project will require purchase of 10 new vans. The company have a choice Option 1 Electric Van Purchase price Running Costs Capital Allowance Residual value 70.000 2,500 per annum 100% on purchase 20.000 end of year 3 Option 2: Internal Combustion Engine Van Purchase price 50,000 Running Costs E 10.000 per annum Capital Allowance 15% per annum (reducing balance method) Residual Value 20,000 end of year 3 Capital allowances are deductible from profits for tax purposes. Tax is charged at 20% of profits, and payable in the following year. Company wide cost of capital is 20% Question One For the tender, select an appropriate management accounting tool to evaluate the data above, and present the implications of the two options. Include a justification of your approach, and a clear recommendation of which option to select. [note: your answer should show your workings and approach, and include a very brief explanation no more than a maximum of 300 words ] 50 Marks Question Two The company have never used all electric vehicles before and are uncertain about the estimated running costs. Estimates range from 1,000 to 5,000 pervan per annum. They are certain about the same estimates for option 2. To what extent does this uncertainty inform the decision to proceed with Option 1 or Option 2? note: your answer should show your workings and approach and include a very brief explanation ne more than maximum of 100 words ]