PP . 6 3 Jupiter, a large candy company, is having great success with its Swan family of candy bars. Due to a number of

PP.63 Jupiter, a large candy company, is having great success with its "Swan" family of candy bars. Due to a number of factors they like to plan their production at least six months into the future. The table below contains their demand projections (in tons) for April through September:
Supply/Demand Info Beginning Apr May Jun Jul Aug Sep
Predicted Sales 57,10049,00047,30050,80049,60056,600
Regular production
Overtime production
Subcontract production
Ending inventory 9,800
Hired employees
Fired employees
Total employees 492
Cost variables are as follows:
Cost Variables
Labor cost/hour $13
Overtime cost/ton $31
Subcontracting cost/ton $24
Holding cost/ton/month $8
Hiring cost/employee $3,600
Firing cost/employee $5,600
Here is some additional relevant (capacity) information:
Capacity Information
Total labor hours/ton 4
Regular production tons/employee/month 100
Max regular production (tons/month)51,800
Max overtime production (tons/month)4,200
Max subcontractor production (tons/month)5,900
Given the above information (and don't overlook beginning number of employees and inventory levels in the first table), create a LEVEL production plan with only the use of regular production and no inventory left over at the end of the six-month period.
What is the regular production cost (over the six months from April through September) for a level production plan? (Display your answer to the nearest whole number.)
What is the total overtime production cost for this production plan? (Display your answer to the nearest whole number.)
What is the total subcontract cost for this production plan? (Display your answer to the nearest whole number.)
What is the total holding cost for this production plan? (Display your answer to the nearest whole number.)
What is the total hire cost for this production plan? (Display your answer to the nearest whole number.)
What is the total fire cost for this production plan? (Display your answer to the nearest whole number.)
What is the total cost (sum of all costs) for this production plan? (Display your answer to the nearest whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Book Of Templates

Authors: Navaid Ur Rehman

1st Edition

9798719847344

More Books

Students also viewed these General Management questions

Question

In which ways would you measure training success? Explain.

Answered: 1 week ago

Question

Evaluate Meyers and Browns approach to career development.

Answered: 1 week ago