Practical Assignment - Project Schedule This assignment continues from the previous assignment (attending school in another country). For this assignment: This week, you will start
Practical Assignment - Project Schedule
This assignment continues from the previous assignment (attending school in another country). For this assignment:
- This week, you will start with your Activity List that you created last week and further that work by creating a Gantt Chart using the MSG software as demonstrated in the on-line tutorials.
- You'll need to ensure that your MSG contains durations, start/end dates, progress status and who's assigned to the work.
- Your MSG schedule should include all of the activities contained in your Activity List.
Overall Feedback
Don't number your activities. Remove the numbering (no marks deducted this time).
Fix the formatting; I suspect that you inserted cells instead of rows. Have a look at the announcement last week I made regarding this assignment. -0.5
I still don't see a Project Management WP with activities. -2.
You needed to create dependencies. You didn't do this. Use Excel formulas. -1
What continues to hurt your mark on this assignment is not listening to the feedback on your activity list assignment. You used your deliverables as WP. Your WP were activities (incorrectly named like activities). You didn't bother to try and rename your WP properly and break those down into activities. You must update the schedule.
5/12
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started