Practice Question 2. A penalty cost of $1090 per week starts at the beginning of week 20 for a project. The project has an overhead
Practice Question 2. A penalty cost of $1090 per week starts at the beginning of week 20 for a project. The project has an overhead cost of 130 per week, and a normal direct cost for the entire project of $ 8320 for a 24 week duration and $10530 for the crashed direct costs for a shorter 16 week duration. If the project manager decided to plan for the project to be completed by the end of week 22, what would be the total project cost (including all costs to the project)