Question
Pre-Assessment for Manager Budget & Business Planning 16 th May, 2023 Case Study: XYZ Construction Company XYZ Communication Nigeria Company is a Techco company specializes
Pre-Assessment for Manager Budget & Business Planning
16th May, 2023
Case Study: XYZ Construction Company XYZ Communication Nigeria Company is a Techco company specializes in providing Technology platform for Banks and Corporate organization. The company is planning to build a new Data Centre in Owo, Ondo State Nigeria and all the four CPUs must come together to produce the budget for the Data Centre. The project will take 3 years to be completed and the contractor will support the platform using Manage Service Operation for the first two years after the platform is delivered.
As the Budget and Business Planning Manager, you have been tasked with a responsibility of preparing a comprehensive budget for the project, instituting budgetary controls, and managing any potential contract price variations during the project's life. In your meeting with the CPUs, the following information were presented;
- Contract Name: Owo Data Centre
- Project Duration/Contract Period: January 2024 - December 2026 (3 years).
- Purchase Order will be issued every January
- In order to manage the Fx impact, payment will be made upfront twice in the year (January and July) and the exchange rate below (Table 1) have been agreed with the supplier.
- It is assumed that the platform has 10 years life span.
- 10 banks already signify interest and have signed contract with XYZ. Contract price is N100m pa (each bank) effective January 1st, 2027
- You have received the RFI in Table 2 below from the supplier.
- All Civil works will be done and completed in year 1
- All IDC materials will be delivered in year 2. Installation is the last phase of the project.
Table 1- Exchange Rate Table agreed with the Supplier
Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | |
2024 | 449 | 457 | 458 | 459 | 460 | 461 | 465 | 467 | 469 | 471 | 473 | 475 |
2025 | 461 | 465 | 467 | 469 | 471 | 473 | 475 | 477 | 479 | 481 | 483 | 485 |
2026 | 471 | 473 | 475 | 477 | 479 | 481 | 483 | 485 | 487 | 489 | 491 | 493 |
2027 | 485 | 487 | 489 | 491 | 493 | 495 | 497 | 499 | 501 | 503 | 505 | 507 |
2028 | 497 | 499 | 501 | 503 | 505 | 507 | 509 | 511 | 513 | 515 | 517 | 519 |
Table 2 (RFI received from the supplier)
Data Centre Items | ||
1 | Annual Routine Maintenance | $265,130 |
2 | Annual Platform Managed Service Operation (MSO) | $120,000 |
3 | Other annual Miscellaneous Items (Operational) | $60,000 |
4 | Project Nephos - Cloud Consumption (implemented before commissioning) | $16,308 |
5 | Critical databases Platform (implemented before commissioning) | $160,000 |
6 | 3 plots of land for the Data Centre | $150,000 |
7 | Civil work for IDC Phase1B Service | $254,420 |
8 | IDC-Equipment Room_Prefab Container | $172,154 |
9 | IDC-Power Room_Prefab Container | $172,154 |
10 | IDC-Power Room_Battery for IT UPS | $100,351 |
11 | Freight and Insurance (CIF Lagos, by sea) | $69,688 |
12 | Installation and commissioning | $150,000 |
Task
- Prepare
- Monthly Opex budget for the relevant years
- Capex budget for all the relevant years. 50 marks
- What is your budgeted EBIT in the first year of operation? 20 marks
- What is the ROI % based on the available information? 15 marks
- What additional document will you request for if you must accept payment in advance. 5 Marks
- Highlight steps you will take in ensuring the budget for the project is submitted for approval at due date. 10 Marks
Submit your report in a PowerPoint and all your workings in excel.
1 hour
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started