Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is

Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows:

Direct materials: 6 pounds at $9 per pound

$

54

Direct labor: 3 hours at $15 per hour

45

Variable overhead: 3 hours at $5 per hour

15

Total standard cost per unit

$

114

The planning budget for March was based on producing and selling 20,000 units. However, during March the company actually produced and sold 25,000 units and incurred the following costs:

a.

Purchased 180,000 pounds of raw materials at a cost of $7.50 per pound. All of this material was used in production.

b.

Direct laborers worked 61,000 hours at a rate of $16 per hour.

c.

Total variable manufacturing overhead for the month was $306,220.

1.

What raw materials cost would be included in the companys planning budget for March?

Raw material cost

2.

What raw materials cost would be included in the companys flexible budget for March?

Raw material cost

3.

What is the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)

Materials price variance

4.

What is the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)

Materials quantity variance

5.

If Preble had purchased 176,000 pounds of materials at $7.50 per pound and used 180,000 pounds in production, what would be the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Do not round intermediate calculations.)

Materials price variance

6.

If Preble had purchased 176,000 pounds of materials at $7.50 per pound and used 180,000 pounds in production, what would be the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Do not round intermediate calculations.)

Materials quantity variance

7.

What direct labor cost would be included in the companys planning budget for March?

Direct labor cost

8.

What direct labor cost would be included in the companys flexible budget for March?

Direct labor cost

8.

What direct labor cost would be included in the companys flexible budget for March?

Direct labor cost

9.

What is the labor rate variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Do not round intermediate calculations.)

Labor rate variance

10.

What is the labor efficiency variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Do not round intermediate calculations.)

Labor efficiency variance

11.

What is the labor spending variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Do not round intermediate calculations.

Labor spending variance

12.

What variable manufacturing overhead cost would be included in the companys planning budget for March?

Variable manufacturing overhead cost

13.

What variable manufacturing overhead cost would be included in the companys flexible budget for March?

Variable manufacturing overhead cost

14.

What is the variable overhead rate variance for March? (Round the actual overhead rate to two decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)

Variable overhead rate variance

15.

What is the variable overhead efficiency variance for March? (Do not round intermediate calculations. Round the actual overhead rate to two decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.).)

Variable overhead efficiency variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Government Auditing Standards

Authors: U.S. Government Accountability Office

1st Edition

B0C9S8NVST, 979-8851147746

More Books

Students also viewed these Accounting questions