Preceded by Problem 2. [10 points] Assume you have the following process for quality control: Activity Time est. (weeks) 15 8 11 14 10 7
Preceded by Problem 2. [10 points] Assume you have the following process for quality control: Activity Time est. (weeks) 15 8 11 14 10 7 . D, E a. Draw the network diagram and identify the critical path in the network. b. Find the slack in activity C. Explain what the slack in activity C means in terms of starting activity E and overall completion time of this process