Prepare network diagram for this project. The standard working week is 40 hours working Monday through Friday, 8 hours each day.Tasks with duration not dependent

Prepare network diagram for this project. The standard working week is 40 hours working Monday through Friday, 8 hours each day.Tasks with duration not dependent on resources assigned are listed as calendar day duration. An example is awaiting arrival of a part in shipment from a supplier.

image text in transcribed
Activity Immediate Predecessor Resource Need / Duration a 80 person hours b a 48 person hours C b 80 person hours a 1 12 person hours e c.d 3 calendar days d 128 person hours g e,f 48 person hours h e 48 person hours gah 64 person hours 4 calendar days k L. 32 person hours

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Achieving Competitive Advantage

Authors: Jeffrey K. Pinto

4th edition

133798070, 978-0133798074

More Books

Students also viewed these General Management questions

Question

Identify the structure for the presentation of

Answered: 1 week ago