Question

1 Approved Answer

Price variation calculation: (Calculator required) You are required to assist the Contract Manager to verify the claim submitted. The contract document states the following conditions:

Price variation calculation: (Calculator required)

You are required to assist the Contract Manager to verify the claim submitted.

The contract document states the following conditions:

1. The awarded contract price is R300.00 per unit

2. The contract states the offer is subject to supplier XYZs pricelist variation.

The contractor when submitting his claim provided the following:

a) Old (Original) pricelist from XYZ Supplier at closing date of tender, the price was R2600 per quantity of 10.

b) The new pricelist from XYZ Supplier is R2864.00 per quantity of 10.

Calculate the new contract price due. (illustrate your answer in detail) = (max 5points)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management With CompTIA Project+

Authors: Joseph Phillips

4th Edition

9781259860300

More Books

Students also viewed these General Management questions