Question

1 Approved Answer

Prince of Wales Production Company planned to use 2 yards of material per unit budgeted at $5 a yard. However, the material actually cost $4.90

Prince of Wales Production Company planned to use 2 yards of material per unit budgeted at $5 a yard. However, the material actually cost $4.90 per yard. The company actually made 4,000 units, although it had planned to make only 3,800 units. Total yards purchased and used for production were 8,900. How much is the total materials variance?

A :

$2,000 F

B :

$4,890 U

C :

$3,610 U

D :

$890 U

show works please

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Security And Auditing Protecting Data Integrity And Accessibility

Authors: Hassan A. Afyouni

1st Edition

0619215593, 9780619215590

More Books

Students also viewed these Accounting questions

Question

Under what conditions is S Answered: 1 week ago

Answered: 1 week ago