PROBLEM 1: An analysis of past janitorial costs indicates that the average janitorial cost is P1.50 per machine hour at an activity level of 40,000
PROBLEM 1:An analysis of past janitorial costs indicates that the average janitorial cost is P1.50 per machine hour at an activity level of 40,000 machine hours and P1.20 per machine hour at an activity level of 50,000 machine hours. Assuming that this activity is within the relevant range, what is the total expected janitorial cost if the activity level is 45,000 machine hours?
PROBLEM 2: The Mix Co. uses the high-low method to estimate the cost function. The information for 2012 is provided below:
Machine-hours Labor Costs
Highest observation of cost driver 500 P15,000
Lowest observation of cost driver 220 6,600
What is the total cost for 400 hours?
PROBLEM 3: Chandler Company produces and sells rattan baskets. The number of drifts produced are the corresponding total production costs for six months, which are representatives for the year, are as follows:
Month Units Produced Production Costs
April 500 P 4,000
May 700 8,000
June 900 6,000
July 600 7,500
August 800 8,500
September 550 7,250
Required: Solve for the variable and fixed cost component using:
a.) High- Low Method
b.) Least- Squares Regression
PROBLEM 4:Monica Company's total overhead costs at various levels of activity are presented below:
Month Machine Hours Total Overhead Costs
April 140,000 P198,000
May 120,000 174,000
June 160,000 222,000
July 180,000 246,000
Assume that the total overhead costs above consist of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 120,000 machine-hour level of activity is:
Utilities (V) P 48,000
Supervisory salaries (F) 21,000
Maintenance (M) 105,000
Total overhead costs P 174,000
V= variable; F = fixed; M = mixed
Monica Company's management wants to break down the maintenance cost into its basic variable and fixed cost elements.
Required:
- As shown above, overhead costs in July amounted to P246,000. Determine how much of this consisted of maintenance cost.
- By means of the high-low method, estimate a cost formula for maintenance.
- Express the company's total overhead costs in the linear equation form Y = a + bX.
- What total overhead costs would you expect to be incurred at an operating activity level of 150,000 machine-hours?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started