Problem 1 Consider the following tasks for a project. Task Time (days) Immediate predecessors A 3 N/A B 2 A C 6 A D 2
Problem 1
Consider the following tasks for a project.
Task | Time (days) | Immediate predecessors |
A | 3 | N/A |
B | 2 | A |
C | 6 | A |
D | 2 | C |
E | 3 | A |
F | 3 | B |
G | 5 | C |
H | 1 | C |
I | 1.5 | F,H |
J | 2 | I |
(a) Draw the project network and determine the critical path(s) using AOA method and determine the critical path. (10 marks)
(b) The project manager felt that CPM should not be used for this project. Instead, the best, worst and most likely time was estimated for each activity and PERT was used. The time to complete the project had a mean of 18.5 days and a standard deviation of 2.15 days.
(i) Determine the probability that is will take more than 20 days to finish the project. (2 marks)
. (ii) The project manager wants to tell the client he is 90% sure the project will be completed by time X. What is the value of X? (3 marks)
Problem 2
Draw project network from Problem 1 using AON method, filling the ES, EF, LS, LF and slack for each node. (10 marks)
The original question is attached below:
(J Problem 19 Consider the following tasks for a project.Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started