Problem 1 ) Decatur Company needs to determine the standard time that it should take a qualified employee to assemble a stapler. An operations analyst
Problem
Decatur Company needs to determine the standard time that it should take a qualified employee to assemble a stapler. An operations analyst has made
observations of an employee completing the task
see table below
and has given the employee a
performance rating for the work done during those observations. For this task, the analyst also has determined that a
job
task time allowance factor should be used in calculating the standard time for the task. Use the information provided to calculate the observed, normal and standard times for the task. Fill in the total in the table and then show your work to the
right of each formula. Round your answers at each step to one decimal point.
points
table
Observation
table
Time
seconds
Total
What is the Mean Observed Time for this task?
Problem
continues on next page. What is the Normal Time for this task?
times
What is the Standard Time for this task?
t
a
s
k
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started