Problem #1: The data related to the activities of a project are given in Table 1. Show the calculations in three tables, the Forward Pass
Problem #1: The data related to the activities of a project are given in Table 1. Show the calculations in three tables, the Forward Pass Table, the Backward Pass Table and the Critical Activity Identification Table. Then answer questions 1 through 22.
Table 1
Activity | A | B | C | D | E | F | G | H | I | J | K |
Immediate Predecessors | -- | -- | -- | A, B | B | D, E | A, E | C, F | F, G | G | H, I |
Activity Time (days) | 9 | 4 | 6 | 7 | 9 | 6 | 7 | 6 | 4 | 9 | 8 |
QUESTION 31
Refer to the problem in question 11.
What is the length of the critical path?
QUESTION 32
Refer to the problem in question 11.
What is thenumber of activities onthe critical path?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started