Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Problem 1: The ETHAN Construction company was the lowest bidder on a specialized equipment contract. The contract bid was P13,125,000 with an estimated cost to

Problem 1:

The ETHAN Construction company was the lowest bidder on a specialized equipment contract. The contract bid was P13,125,000 with an estimated cost to complete the project of P7,800,000. The contract period was 35 months beginning January 1, 2017. The company uses cost to cost method to estimated profits. A record of construction activities for the years 2017 to 2019 follows:

2017 2018 2019

Actual cost incurred to date P6,562,500 10,968,750 116,250,000

Esimated cost to complete 4,375,000 1,218,750 -

Progress billings 3,000,000 12,000,000 13,125,000

Cash receipts during the year 5,625,000 3,750,000 3,750,000

Using percentage-of-completion method, compute for the following:

1. How much is the realized gross profit in 2017, 2018 and 2019?

2. How much is the Revenue earned in 2018?

3. How much is the CIP net in 2018?

4. How much is the CIP net in 2019?

Using zero-profit method (cost recovery), compute for the following:

5. How much is the realized gross profit in 2017, 2018 and 2019?

6. How much is the Revenue earned in 2018?

7. How much is the CIP net in 2018?

8. How much is the CIP net in 2019?

Problem 2:

ETON CONSTRUCTION COMPANY is recognizing income from long term construction contracts. In 2013, ETON entered into a fixed-price contract to construct a fly-over connecting Luzon and Mindanao for P65,000,000. Estimated costs and contract costs incurred up to 2016 were as follows:

Year Costs incurred Estimated cost at completion Progress Billings

2013 P15,000,000 P60,000,000 P15,000,000

2014 6,700,000 62,000,000 6,000,000

2015 24,500,000 66,000,000 25,000,000

2016 16,800,000 63,000,000 19,000,000

Using percentage-of-completion method, compute for the following:

1. How much is the realized gross or (loss) profit in 2015 and 2016?

2. How much is the Revenue earned in 2015 under percentage of completion based on gross profit?

3. How much is the Revenue earned in 2015 under percentage of completion based on Contract Price (Revenue)?

4. How much is the CIP net in 2016?

5. How much is the actual cost of construction in 2015 for income statement presentation purposes?

Problem 3

On July 1, 2017, Dinar obtained a contract to construct a building. The building was estimated to be built at a total cost of P15,000,000 and is scheduled for completion on October 2019. The contract contains a penalty clause to the effect that the other party was to deduct P35,000 from the contract price for each week of delay. On the other hand, if the contractor was able to finish the building earlier than agreed, it will be rewarded an amount equal to P50,000 for every month of early completion. Furthermore, cost escalation clause was included in the contract. In 2018, the estimated costs of particular construction material amounting to P520,000 were bought for P780,000. The increase in the contract price related to this cost escalation was approved by the client. Completion was delayed for 4 weeks. The records show:

2017 2018 2019

Costs incurred P1,750,000 6,440,000 1,085,000

Estimated cost to complete 7,000,000 1,810,000 --

Progress billings 1,400,000 15,225,000 4,200,000

1. What is the Original Contract Price 2017?

2. What is the Original Contract Price 2018?

3. What is the CIP net as of 2018?

Problem 4

CABUGERO DEVELOPMENT COMPANY., started work on a construction contract in 2018. The contract price is P10M. However, if the cumulative inflation reaches or exceeds 25%, the contract price shall be adjusted upward by 10%. Cost escalations on the contract are probable as to recovery. Additional information on the contract is shown below:

2018 2019

Costs incurred to date 2,400,000 4,500,000

Estimated cost at completion 6,000,000 6,000,000

Cumulative inflation rate 18% 27%

1. Compute for the percentage of completion during the year 2018.

2. Compute for the percentage of completion during the year 2019.

3. What is the contract price in 2018?

4. What is the contract price in 2019?

5. What is the realized gross profit in 2018?

6. What is the realized gross profit in 2019?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Chapters 1-13

Authors: Carl Warren

27th Edition

1337272108, 978-1337272100

More Books

Students also viewed these Accounting questions

Question

1. Build trust and share information with others.

Answered: 1 week ago