Problem 12-09 (Algorithmic) A project has four activities(A,B, C, andD)that must be performed sequentially. The probability distributions for the time required to complete each of
Problem 12-09 (Algorithmic)
A project has four activities(A,B, C, andD)that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:
Activity Activity Time(weeks) Probability
A 4 0.27
5 0.37
6 0.26
7 0.10
B 6 0.16
8 0.54
10 0.30
C 10 0.11
12 0.26
14 0.36
16 0.22
18 0.05
D 10 0.66
12 0.34
a. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
Activity Base case Worst case Bestcase
A _______weeks _______weeks _______weeks
B _______weeks _______weeks _______weeks
C _______weeks _______weeks _______weeks
D _______weeks _______weeks _______weeks
TOTAL _______weeks _______weeks _______weeks
b. Use the random numbers 0.6361, 0.9453, 0.651 and 0.7795 to simulate the completion time of the project in weeks.
Activity Random Number Completion Time
A 0.6361 _______weeks
B 0.9453 _______weeks
C 0.651 _______weeks
D 0.7795 _______weeks
TOTAL _______weeks
c. Discuss how simulation could be used to estimate the probability that the project can be completed in weeks or less.
Simulation provides a distribution of project completion times. The
_______________ (mean/percentage) of times weeks and under can be used to estimate the probability that the project will be completed within weeks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started