Question
Problem 12-16 Measures of Internal Business Process Performance [LO12-3] MacIntyre Fabrications, Ltd., of Aberdeen, Scotland, has recently begun a continuous improvement campaign in conjunction with
Problem 12-16 Measures of Internal Business Process Performance [LO12-3]
MacIntyre Fabrications, Ltd., of Aberdeen, Scotland, has recently begun a continuous improvement campaign in conjunction with a move toward Lean Production. Management has developed new performance measures as part of this campaign. The following operating data have been gathered over the last four months: |
Month | |||||
1 | 2 | 3 | 4 | ||
Throughput time | ? | ? | ? | ? | |
Manufacturing cycle efficiency | ? | ? | ? | ? | |
Delivery cycle time | ? | ? | ? | ? | |
Percentage of on-time deliveries | 72% | 73% | 78% | 85% | |
Total sales (units) | 10,540 | 10,570 | 10,550 | 10,490 | |
Management would like to know the companys throughput time, manufacturing cycle efficiency, and delivery cycle time. The data to compute these measures have been gathered and appear below: |
Month | |||||||||
1 | 2 | 3 | 4 | ||||||
Move time per unit, in days | 0.5 | 0.5 | 0.4 | 0.5 | |||||
Process time per unit, in days | 0.6 | 0.5 | 0.5 | 0.4 | |||||
Wait time per order before start of production, in days | 9.6 | 8.7 | 5.3 | 4.7 | |||||
Queue time per unit, in days | 3.6 | 3.6 | 2.6 | 1.7 | |||||
Inspection time per unit, in days | 0.7 | 0.7 | 0.4 | 0.3 | |||||
Required: | |||
1. | Complete the below table to calculate throughput time, manufacturing cycle efficiency (MCE), and delivery cycle time. for each month. (Round your answers to 1 decimal place.)
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started