Question
Problem 17-12 (Static) A project manager has compiled a list of major activities that will be required to install a computer information system in her
Problem 17-12 (Static)
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. Use Table B1 and Table B2.
Activity | Immediate Predecessor | Estimated Times (weeks) |
A | 2-4-6 | |
D | A | 6-8-10 |
E | D | 7-9-12 |
H | E | 2-3-5 |
F | A | 3-4-8 |
G | F | 5-7-9 |
B | 2-2-3 | |
I | B | 2-3-6 |
J | I | 3-4-5 |
K | J | 4-5-8 |
C | 5-8-12 | |
M | C | 1-1-1 |
N | M | 6-7-11 |
O | N | 8-9-13 |
End | H, G, K, O | |
Click here for the Excel Data File
a. Determine the mean and standard deviation for each of the following paths in the project. (Round Mean and Standard Deviation to 2 decimal places.)
b. If the project finishes within 26 weeks of its start, the project manager receives a $1,000 bonus. What is the probability of a $1,000 bonus? (Round z-value to 2 decimal places, and probability to 4 decimal places.)
c. If the project finishes within 27 weeks of its start, the project manager receives a $500 bonus. What is the probability of a $500 bonus? (Round z-value to 2 decimal places, and probability to 4 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started