Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3 [The following information applies to the questions displayed below.] Craft Pro Machining produces machine
Problem 17-3A Applying activity-based costing LO P1, P3, A1, A2, C3
[The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records.
Production Activity | Indirect Labor | Indirect Materials | Other Overhead | ||||||||
Grinding | $ | 400,000 | |||||||||
Polishing | $ | 110,000 | |||||||||
Product modification | 500,000 | ||||||||||
Providing power | $ | 215,000 | |||||||||
System calibration | 460,000 | ||||||||||
Additional information on the drivers for its production activities follows.
Grinding | 14,000 | machine hours |
Polishing | 14,000 | machine hours |
Product modification | 1,600 | engineering hours |
Providing power | 18,000 | direct labor hours |
System calibration | 950 | batches |
Job 3175 | Job 4286 | |||
Number of units | 180 | units | 2,250 | units |
Machine hours | 500 | MH | 5,000 | MH |
Engineering hours | 28 | eng. hours | 28 | eng. hours |
Batches | 30 | batches | 90 | batches |
Direct labor hours | 440 | DLH | 3,960 | DLH |
Problem 17-3A Part 5
5. If the company uses a plantwide overhead rate based on direct labor hours, what is the overhead cost for each unit of Job 3175? Of Job 4286? (Do not round intermediate calculations. Round "OH Cost per unit" answers to 2 decimal places.)
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started