Problem 18-10 On March 1, 2020, Pearl Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of

Problem 18-10

On March 1, 2020, Pearl Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,360,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below:

2020

2021

2022

Contract costs incurred during the year $2,615,800 $2,633,000 $2,041,200
Estimated costs to complete the contract at 12/31 3,764,200 2,041,200 0
Billings to Fabrik during the year 3,230,000 3,500,000 1,630,000
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

2020

Profit / (Loss) Recognized in 2020Costs IncurredPercent CompleteRevenue RecognizedEstimated Total CostsCosts to date (12/31/20)Estimated Costs to Complete

$

Profit / (Loss) Recognized in 2020Percent CompleteEstimated Total CostsRevenue RecognizedCosts to date (12/31/20)Estimated Costs to CompleteCosts Incurred

Profit / (Loss) Recognized in 2020 Percent Complete Revenue Recognized Estimated Costs to Complete Estimated Total Costs Costs Incurred Costs to date (12/31/20)

$

Profit / (Loss) Recognized in 2020Costs to date (12/31/20)Estimated Total CostsCosts IncurredEstimated Costs to CompletePercent CompleteRevenue Recognized

%

Costs to date (12/31/20)Estimated Costs to CompleteEstimated Total CostsPercent CompleteRevenue RecognizedCosts IncurredProfit / (Loss) Recognized in 2020

$

Percent CompleteCosts to date (12/31/20)Costs IncurredProfit / (Loss) Recognized in 2020Estimated Costs to CompleteRevenue RecognizedEstimated Total Costs

Percent CompleteEstimated Costs to CompleteRevenue RecognizedCosts IncurredProfit / (Loss) Recognized in 2020Costs to date (12/31/20)Estimated Total Costs

$

2021

Estimated Total CostsPercent CompleteRevenue Recognized in 2021Profit / (Loss) Recognized in 2020Costs Incurred in 2021Costs to date (12/31/21)Estimated Costs to Complete

$

Estimated Costs to CompleteEstimated Total CostsRevenue Recognized in 2021Costs to date (12/31/21)Costs Incurred in 2021Profit / (Loss) Recognized in 2020Percent Complete

Estimated Costs to Complete Costs to date (12/31/21) Estimated Total Costs Revenue Recognized in 2021 Costs Incurred in 2021 Percent Complete Profit / (Loss) Recognized in 2020

$

Costs to date (12/31/21)Estimated Total CostsEstimated Costs to CompletePercent CompleteRevenue Recognized in 2021Costs Incurred in 2021Profit / (Loss) Recognized in 2020

%

Revenue Recognized in 2021Percent CompleteEstimated Total CostsCosts Incurred in 2021Estimated Costs to CompleteProfit / (Loss) Recognized in 2020Costs to date (12/31/21)

$

Profit / (Loss) Recognized in 2020Costs Incurred in 2021Estimated Costs to CompleteCosts to date (12/31/21)Estimated Total CostsPercent CompleteRevenue Recognized in 2021

Costs Incurred in 2021 Estimated Total Costs Revenue Recognized Costs to date (12/31/21) Percent Complete Profit / (Loss) Recognized in 2021 Estimated Costs to Complete

$

2022

Total Profit on ContractTotal Costs IncurredProfit Previously RecognizedProfit / (Loss) Recognized in 2022Total Revenue Recognized

$

Total Revenue RecognizedTotal Costs IncurredTotal Profit on ContractProfit Previously RecognizedProfit / (Loss) Recognized in 2022

Total Costs IncurredProfit Previously RecognizedTotal Revenue RecognizedTotal Profit on ContractProfit / (Loss) Recognized in 2022

AddLess

:

Total Profit on ContractTotal Revenue RecognizedProfit Previously RecognizedProfit / (Loss) Recognized in 2022Total Costs Incurred

Total Revenue RecognizedTotal Profit on ContractTotal Costs IncurredProfit / (Loss) Recognized in 2022Profit Previously Recognized

$

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
2020 $

2021 $

2022 $

Click if you would like to Show Work for this question:

Open Show Work

Question Attempts: Unlimited

SAVE FOR LATER

SUBMIT ANSWER

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Certified Internal Auditor CIA Practice Of Internal Auditing Part 2- 2019

Authors: Muhammad Zain

1st Edition

1093798459, 978-1093798456

More Books

Students also viewed these Accounting questions