Problem 18-11 On July 1, 2017, Marigold Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of
Problem 18-11
On July 1, 2017, Marigold Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Marigold estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019.
At 12/31/17 | At 12/31/18 | At 12/31/19 | ||||
Contract costs incurred to date | $286,900 | $1,122,900 | $2,066,700 | |||
Estimated costs to complete the contract | 1,223,100 | 847,100 | 0 | |||
Billings to Gumbel | 300,000 | 1,100,000 | 1,830,000 |
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank. Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started