Question
Problem 19-14 Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. The monthly forecasts for
Problem 19-14
Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. |
The monthly forecasts for Product X for January, February, and March are 960, 1,500, and 1,170, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning inventory is 490 units. |
Storage cost is $4 per unit per month based on ending inventory level, standard pay rate is $4 per hour, hiring and training cost is $160 per worker, layoff cost is $260 per worker, and worker productivity is 0.1 unit per hour. Assume that you start off with 42 workers and that they work 8 hours per day. (Leave no cells blank - be certain to enter "0" wherever required. Input all values as positive values. Round Workers Required up to next higher whole number. Round all other variables to nearest whole number.) |
January | February | March | |
Forecast | 960 | 1,500 | 1,170 |
Safety stock | |||
Beginning inventory | |||
Net production required | |||
Workers required | |||
Hired | |||
Laid off | |||
Actual production | |||
Ending inventory | |||
January | February | March | |
Labor cost | $ | $ | $ |
Inventory cost | |||
Hiring cost | |||
Layoff cost | |||
Total cost | $ | $ | $ |
Total | $ | ||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started