Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Problem 20.23 (Algorithmic) EOQ, Safety Stock, Lead Time, Batch Size, and JIT Bateman Company produces helmets for drivers of motorcycles. Helmets are produced in batches

Problem 20.23 (Algorithmic) EOQ, Safety Stock, Lead Time, Batch Size, and JIT

Bateman Company produces helmets for drivers of motorcycles. Helmets are produced in batches according to model and size. Although the setup and production time vary for each model, the smallest lead time is six days. The most popular model, Model HA2, takes two days for setup, and the production rate is 900 units per day. The expected annual demand for the model is 43,200 units. Demand for the model, however, can reach 54,000 units. The cost of carrying one HA2 helmet is $3 per unit. The setup cost is $7,200. Bateman chooses its batch size based on the economic order quantity criterion. Expected annual demand is used to compute the EOQ.

Recently, Bateman has encountered some stiff competitionespecially from foreign sources. Some of the foreign competitors have been able to produce and deliver the helmets to retailers in half the time it takes Bateman to produce. For example, a large retailer recently requested a delivery of 14,400 Model HA2 helmets with the stipulation that the helmets be delivered within seven working days. Bateman had 3,600 units of HA2 in stock. Bateman informed the potential customer that it could deliver 3,600 units immediately and the other 10,800 units in about 14 working dayswith the possibility of interim partial orders being delivered. The customer declined the offer indicating that the total order had to be delivered within seven working days so that its stores could take advantage of some special local conditions. The customer expressed regret and indicated that it would accept the order from another competitor who could satisfy the time requirements.

Required:

1. Calculate the optimal batch size for Model HA2 using the EOQ model. Round your answer to the nearest whole number if rounding is required.

units

Was Bateman's response to the customer right? Would it take the time indicated to produce the number of units wanted by the customer?

- Select your answer -YesNoItem 2

2. Upon learning of the lost order, the marketing manager grumbled about Bateman's inventory policy, "We lost the order because we didn't have sufficient inventory. We need to carry more units in inventory to deal with unexpected orders like these."

Do you agree or disagree?

- Select your answer -AgreeDisagreeItem 3

How much additional inventory would have been needed to meet the customer's requirements?

additional units

If it is common for the excess demand to occur from just a few very large orders during the year, will Bateman need to carry more inventory in order to meet the demand? - Select your answer -YesNoItem 5

3. Fenton Gray, the head of industrial engineering, reacted differently to the lost order: "Our problem is more complex than insufficient inventory. I know that our foreign competitors carry much less inventory than we do. What we need to do is decrease the lead time. I have been studying this problem, and my staff has found a way to reduce setup time for Model HA2 from two days to 1.5 hours. Using this new procedure, setup cost can be reduced to about $94. Also, by rearranging the plant layout for this productcreating what are called manufacturing cellswe can increase the production rate from 900 units per day to about 2,400 units per day. This is done simply by eliminating a lot of move time and waiting timeboth non-value-added activities." Assume that there are eight hours available in each workday.

Assume that the engineer's estimates are on target. Compute the new optimal batch size (using the EOQ formula). Round your answer to the nearest whole number.

units

What is the new lead time? Round your answer to one decimal place.

hours

Given this new information, would Bateman have been able to meet the customer's time requirements? - Select your answer -YesNoItem 8

4. Suppose that the setup time and cost are reduced to 0.5 hour and $10, respectively. What is the batch size now? Round your answer to the nearest whole number.

units

As setup time approaches zero and the setup cost becomes negligible, what does this imply? Assume, for example, that it takes five minutes to set up, and costs are about $0.864 per setup. - Select your answer -Bateman can reduce inventories, and may even be able to produce on demandBateman will still need to increase its inventory levels to meet excess demandItem 10

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operational Guidelines For Postmortem Examinations And Auditing

Authors: O.P. Murty, O.P Murty

1st Edition

8123924437, 978-8123924434

More Books

Students also viewed these Accounting questions