Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, C2 [The following information applies

Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, C2

[The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product.

Direct materials (3.0 Ibs. @ $4.00 per Ib.) $ 12.00
Direct labor (1.7 hrs. @ $13.00 per hr.) 22.10
Overhead (1.7 hrs. @ $18.50 per hr.) 31.45
Total standard cost $ 65.55

The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factorys capacity of 20,000 units per month. Following are the companys budgeted overhead costs per month at the 75% capacity level.

Overhead Budget (75% Capacity)
Variable overhead costs
Indirect materials $ 15,000
Indirect labor 75,000
Power

15,000

Repairs and maintenance 30,000
Total variable overhead costs $ 135,000
Fixed overhead costs
DepreciationBuilding 23,000
DepreciationMachinery 71,000
Taxes and insurance 16,000
Supervision 226,750
Total fixed overhead costs 336,750
Total overhead costs $ 471,750

The company incurred the following actual costs when it operated at 75% of capacity in October.

Direct materials (46,000 Ibs. @ $4.10 per lb.) $ 188,600
Direct labor (28,000 hrs. @ $13.30 per hr.) 372,400
Overhead costs
Indirect materials $ 41,250
Indirect labor 176,800
Power 17,250
Repairs and maintenance 34,500
DepreciationBuilding 23,000
DepreciationMachinery 95,850
Taxes and insurance 14,400
Supervision 226,750 629,800
Total costs $ 1,190,800

Problem 21-3A Part 1&2

Required: 1&2. Prepare flexible overhead budgets for October showing the amounts of each variable and fixed cost at the 65%, 75%, and 85% capacity levels and classify all items listed in the fixed budget as variable or fixed.

ANTUAN COMPANY
Flexible Overhead Budgets
For Month Ended October 31
Flexible Budget Flexible Budget for
Variable Amount per Unit Total Fixed Cost 65% of capacity 75% of capacity 85% of capacity
Sales (in units)
Variable overhead costs
Fixed overhead costs
Total overhead costs

3. Compute the direct materials cost variance, including its price and quantity variances. AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price

Actual Cost Standard Cost

4. Compute the direct labor cost variance, including its rate and efficiency variances. AH = Actual Hours SH = Standard Hours AR = Actual Rate SR = Standard Rate

Actual Cost Standard Cost

Part 5. Prepare a detailed overhead variance report that shows the variances for individual items of overhead.

ANTUAN COMPANY KWIKEZE COMPANY KWIKEZE COMPANY KWIKEZE COMPANY KWIKEZE COMPANY
Overhead Variance Report
For Month Ended October 31
Expected production volume
Production level achieved
Volume variance
Flexible Budget Actual Results Variances Fav. / Unfav.
Variable costs
Fixed costs
Total overhead costs

***This is all ONE question that has five parts. Please show all five parts.***

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting For Managers Interpreting Accounting Information For Decision Making

Authors: Paul M. Collier

5th Edition

111900294X, 978-1119002949

Students also viewed these Accounting questions

Question

3. Use personal best goals, not between-student competition.

Answered: 1 week ago