Problem 21-4A Computation of materials, labor, and overhead variances LO P2, P3 [The following information applies to the questions displayed below.] Trico Company set the

Problem 21-4A Computation of materials, labor, and overhead variances LO P2, P3

[The following information applies to the questions displayed below.]

Trico Company set the following standard unit costs for its single product.

Direct materials (26 Ibs. @ $5 per Ib.) $ 130.00
Direct labor (10 hrs. @ $10 per hr.) 100.00
Factory overheadvariable (10 hrs. @ $6 per hr.) 60.00
Factory overheadfixed (10 hrs. @ $9 per hr.) 90.00
Total standard cost $ 380.00

The predetermined overhead rate is based on a planned operating volume of 50% of the productive capacity of 60,000 units per quarter. The following flexible budget information is available.

Operating Levels
40% 50% 60%
Production in units 24,000 30,000 36,000
Standard direct labor hours 240,000 300,000 360,000
Budgeted overhead
Fixed factory overhead $ 2,700,000 $ 2,700,000 $ 2,700,000
Variable factory overhead $ 1,440,000 $ 1,800,000 $ 2,160,000

During the current quarter, the company operated at 60% of capacity and produced 36,000 units of product; actual direct labor totaled 353,000 hours. Units produced were assigned the following standard costs:

Direct materials (936,000 Ibs. @ $5 per Ib.) $ 4,680,000
Direct labor (360,000 hrs. @ $10 per hr.) 3,600,000
Factory overhead (360,000 hrs. @ $15 per hr.) 5,400,000
Total standard cost $ 13,680,000

Actual costs incurred during the current quarter follow:

Direct materials (931,000 Ibs. @ $5.10 per lb.) $ 4,748,100
Direct labor (353,000 hrs. @ $9.75 per hr.) 3,441,750
Fixed factory overhead costs 3,130,377
Variable factory overhead costs 2,930,566
Total actual costs $ 14,250,793

Problem 21-4A Part 1

Required:
1.

Compute the direct materials cost variance, including its price and quantity variances.

Problem 21-4A Part 2

2.

Compute the direct labor variance, including its rate and efficiency variances.

Problem 21-4A Part 3

3.

Compute the overhead controllable and volume variances.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Joe Hoyle, Thomas Schaefer, Timothy Doupnik

10th edition

0-07-794127-6, 978-0-07-79412, 978-0077431808

Students also viewed these Accounting questions