Problem 3. Calculating IRR for Cash Flows: Calculate the internal rate of return for the cash flows of the two projects in the table below.
Problem 3. Calculating IRR for Cash Flows: Calculate the internal rate of return for the cash flows of the two projects in the table below.
Year | Project A | Project B |
0 | -4600 | -3500 |
1 | 1400 | 1250 |
2 | 2200 | 1800 |
3 | 2700 | 1600 |