Problem 5 Using the following project information, calculate the expected time for each of the project activities. Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates

Problem 5

Using the following project information, calculate the expected time for each of the project activities.

Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)
A 2 6 9 none
B 4 6 7 A
C 4 7 12 A
D 5 5 10 B
E 6 11 17 C
F 4 5 5 D,E
G 4 5 10 D,E
H 4 6 11 F
I 6 9 12 G
J 3 3 3 H,I

(Round your answers to 2 decimal places, the tolerance is +/-0.01)

Activity Expected Time
A
B
C
D
E
F
G
H
I
J

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Numerical Analysis

Authors: Richard L. Burden, J. Douglas Faires

9th edition

538733519, 978-1133169338, 1133169333, 978-0538733519

More Books

Students also viewed these Mathematics questions

Question

The trim method of the string class removes..........?

Answered: 1 week ago

Question

Which type of data is not accessed in a derived class?

Answered: 1 week ago

Question

India experiences which type of climate?

Answered: 1 week ago