Problem 5-10 Percentage-of-completion method [LO5-8, 5-9] In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
Problem 5-10 Percentage-of-completion method [LO5-8, 5-9]
In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows: |
2016 | 2017 | 2018 | |||||||
Cost incurred during the year | $ | 2,059,000 | $ | 2,627,000 | $ | 2,655,400 | |||
Estimated costs to complete as of year-end | 5,041,000 | 2,414,000 | 0 | ||||||
Billings during the year | 2,190,000 | 2,496,000 | 5,314,000 | ||||||
Cash collections during the year | 1,895,000 | 2,400,000 | 5,705,000 | ||||||
|
Westgate recognizes revenue over time according to percentage of completion. |
Required: |
1. | Calculate the amount of revenue and gross profit to be recognized in each of the three years |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started