Problem 5-10 Percentage-of-completion method [LO5-8, 5-9] In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for

Problem 5-10 Percentage-of-completion method [LO5-8, 5-9]

In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows:

2016 2017 2018
Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400
Estimated costs to complete as of year-end 5,041,000 2,414,000 0
Billings during the year 2,190,000 2,496,000 5,314,000
Cash collections during the year 1,895,000 2,400,000 5,705,000

Westgate recognizes revenue over time according to percentage of completion.

Required:

1.

Calculate the amount of revenue and gross profit to be recognized in each of the three years

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Certificate Of Cloud Auditing Knowledge Study Guide

Authors: Isaca

1st Edition

1604208619, 978-1604208610

More Books

Students also viewed these Accounting questions

Question

1. Describe the power of nonverbal communication

Answered: 1 week ago

Question

2. Outline the functions of nonverbal communication

Answered: 1 week ago