Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Problem 6- Please use EXCEL SOLVER ONLY using the STARTUP FILE given. Show all the steps and formulas B H K M Crash Information Crash

image text in transcribedimage text in transcribed

Problem 6-

image text in transcribed

Please use EXCEL SOLVER ONLY using the STARTUP FILE given. Show all the steps and formulas

B H K M Crash Information Crash Possible Predecessors Cost per Month 1 2 Activity 3 1 4. 2 5 3 6 4 7 5 8 6 9 7 10 8 11 9 12 10 13 11 14 12 15 16 Activity 17 1 18 2 19 3 20 4 21 5 D E F G Activity Time (months) Activity Costs Normal Crash Actual Time Normal Crash Crash Actual 8 5 700 1200 10 9 1600 2000 9 7 900 1500 4 2 500 700 6 3 500 900 S 4 500 800 7 5 700 1000 15 12 1400 2000 12 10 1800 2300 4 3 500 800 7 6 800 1400 ES EF LS LF Slack Critical 22 6 7 23 24 25 8 26 9 10 11 12 27 28 Total number of Months 29 30 31 32 Crash Costs 33 37. The following table provides the crash data for the network project described in Problem 6: Activity Time (months) Activity Cost ($1,000s) Activity Normal Crash Normal Crash 1 2 3 8 10 9 5 9 7 4 5 6 4 6 2 3 $ 700 1,600 900 500 500 500 700 1,400 1,800 1,400 500 800 5 7 15 12 18 4 7 7 $1,200 2,000 1,500 700 900 800 1,000 2,000 2,300 3,200 800 1,400 4 5 12 10 14 8 9 10 11 12 3 6 Using the computer, crash the network to 32 months. Indicate the first critical path activities and then the cost of crashing the network. Problem Given the following network, with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path and the project duration. 8 10 18 5 6 Start 2 10 12 7 Finish 5 15 12 11 4 3 7 B H K M Crash Information Crash Possible Predecessors Cost per Month 1 2 Activity 3 1 4. 2 5 3 6 4 7 5 8 6 9 7 10 8 11 9 12 10 13 11 14 12 15 16 Activity 17 1 18 2 19 3 20 4 21 5 D E F G Activity Time (months) Activity Costs Normal Crash Actual Time Normal Crash Crash Actual 8 5 700 1200 10 9 1600 2000 9 7 900 1500 4 2 500 700 6 3 500 900 S 4 500 800 7 5 700 1000 15 12 1400 2000 12 10 1800 2300 4 3 500 800 7 6 800 1400 ES EF LS LF Slack Critical 22 6 7 23 24 25 8 26 9 10 11 12 27 28 Total number of Months 29 30 31 32 Crash Costs 33 37. The following table provides the crash data for the network project described in Problem 6: Activity Time (months) Activity Cost ($1,000s) Activity Normal Crash Normal Crash 1 2 3 8 10 9 5 9 7 4 5 6 4 6 2 3 $ 700 1,600 900 500 500 500 700 1,400 1,800 1,400 500 800 5 7 15 12 18 4 7 7 $1,200 2,000 1,500 700 900 800 1,000 2,000 2,300 3,200 800 1,400 4 5 12 10 14 8 9 10 11 12 3 6 Using the computer, crash the network to 32 months. Indicate the first critical path activities and then the cost of crashing the network. Problem Given the following network, with activity times in months, determine the earliest and latest activity times and slack for each activity. Indicate the critical path and the project duration. 8 10 18 5 6 Start 2 10 12 7 Finish 5 15 12 11 4 3 7

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Algebra With Modeling And Visualization

Authors: Gary Rockswold

6th Edition

0134418042, 978-0134418049

More Books

Students also viewed these Accounting questions

Question

Why is staffing so important to organizations?

Answered: 1 week ago

Question

a sin(2x) x Let f(x)=2x+1 In(be)

Answered: 1 week ago

Question

Define self-esteem and discuss its impact on your life.

Answered: 1 week ago

Question

Discuss how selfesteem is developed.

Answered: 1 week ago