Problem 6: Using the information in the table below, determine how much of the supplies variance is due to a change in volume. Then select
Problem 6: Using the information in the table below, determine how much of the supplies variance is due to a change in volume. Then select the letter from the list below that shows the correct answer. Budgeted Actual Variance Volume 1,000 1,100 100 Supplies $10,000 $12,750 $2,750 Fixed labor $20,000 $22,250 $2,250 a) $ 900 b) $1,000 c) $1,050 d) $1,250 e) $1,500