Question
1 Approved Answer
Problem 6.2 Activity Immediate PredecessorsTime (Weeks) 1-4 212 314 413 52, 35 636 742 853 96, 75 108, 97 ______________________________________________ a.Draw the network. b.Find the
Problem 6.2
Activity Immediate PredecessorsTime (Weeks)
1-4
212
314
413
52, 35
636
742
853
96, 75
108, 97
______________________________________________
a.Draw the network.
b.Find the critical path.
c.If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started