Problem 6-21 (Algo) Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes: TASK ELEMENT TIME (MINUTES) A 1 B

Problem 6-21 (Algo) Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes: TASK ELEMENT TIME (MINUTES) A 1 B 1 C 2 D E F G_ H I 1 3 1 1 2 1 Efficiency PRECEDING TASKS % A B B Given a cycle time of 4 minutes, develop two alternative layouts. Use the longest task time rule and the largest number of following tasks as a secondary criterion. What is the highest efficiency of your layout, assuming the 4-minute cycle time? Note: Enter your answer as a percentage rounded to 2 decimal places. C, D A F G E, H
image text in transcribed
please help :)
Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes: Given a cycle time of 4 minutes, develop two alternative layouts. Use the longest task time rule and the largest number of following tasks as a secondary criterion. What is the highest efficiency of your layout, assuming the 4 -minute cycle time? Note: Enter your answer as a percentage rounded to 2 decimal places

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these General Management questions