Problem 7-4 . Make-or-buy Decision [LO 1] For most construction projects, Bradley Heating and Cooling buys sheet metal and forms the metal into heating/cooling ducts

Problem 7-4. Make-or-buy Decision [LO 1] For most construction projects, Bradley Heating and Cooling buys sheet metal and forms the metal into heating/cooling ducts as needed. The company estimates the costs of making and installing ductwork for the Kerry Park shopping mall to be as follows: Materials$35,000

Labor to form ductwork 4,000

Labor to install ductwork 10,000

Miscellaneous variable costs 1,500

Fixed costs allocated based on labor hours 3,000

Total $53,500

The fixed costs relate to the company's building, equipment, and office staff. The company plans to bill the Kerry Park developer $68,000 for services. Bradley is currently behind schedule on other projects and is paying a late penalty of $1,200 per day. Walt Bradley, the owner of Bradley Heating and Cooling, is considering ordering prefabricated ductwork for the Kerry Park job. The prefabricated ductwork will cost $42,000 (including the cost of sheet metal). If Walt buys the prefabricated ductwork, he'll be able to reassign workers to another project and avoid five days of late fees.

Should Bradley make the ductwork or buy it prefabricated?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Strategy

Authors: Gerry Johnson, Kevan Scholes, Richard Whittington

2nd Edition

0273713108, 9780273713104

More Books

Students also viewed these Accounting questions