Problem 7-4A Manufacturing: Preparation of a complete master budget LO P1, P2, P3 The management of Zigby Manufacturing prepared the following estimated balance sheet for

Problem 7-4A Manufacturing: Preparation of a complete master budget LO P1, P2, P3

The management of Zigby Manufacturing prepared the following estimated balance sheet for March 2017:

ZIGBY MANUFACTURING Estimated Balance Sheet March 31, 2017
Assets
Cash $ 80,000
Accounts receivable 364,000
Raw materials inventory 96,000
Finished goods inventory 364,800
Total current assets 904,800
Equipment, gross 610,000
Accumulated depreciation (155,000 )
Equipment, net 455,000
Total assets $ 1,359,800
Liabilities and Equity
Accounts payable $ 195,500
Short-term notes payable 17,000
Total current liabilities 212,500
Long-term note payable 510,000
Total liabilities 722,500
Common stock 340,000
Retained earnings 297,300
Total stockholders equity 637,300
Total liabilities and equity $ 1,359,800

To prepare a master budget for April, May, and June of 2017, management gathers the following information:

  1. Sales for March total 20,000 units. Forecasted sales in units are as follows: April, 20,000; May, 19,000; June, 19,500; and July, 20,000. Sales of 245,000 units are forecasted for the entire year. The products selling price is $26.00 per unit and its total product cost is $22.80 per unit.
  2. Company policy calls for a given months ending raw materials inventory to equal 50% of the next months materials requirements. The March 31 raw materials inventory is 4,800 units, which complies with the policy. The expected June 30 ending raw materials inventory is 4,500 units. Raw materials cost $20 per unit. Each finished unit requires 0.50 units of raw materials.
  3. Company policy calls for a given months ending finished goods inventory to equal 80% of the next months expected unit sales. The March 31 finished goods inventory is 16,000 units, which complies with the policy.
  4. Each finished unit requires 0.50 hours of direct labor at a rate of $20 per hour.
  5. Overhead is allocated based on direct labor hours. The predetermined variable overhead rate is $3.20 per direct labor hour. Depreciation of $23,400 per month is treated as fixed factory overhead.
  6. Sales representatives commissions are 6% of sales and are paid in the month of the sales. The sales managers monthly salary is $3,500.
  7. Monthly general and administrative expenses include $17,000 administrative salaries and 0.9% monthly interest on the long-term note payable.
  8. The company expects 30% of sales to be for cash and the remaining 70% on credit. Receivables are collected in full in the month following the sale (none are collected in the month of the sale).
  9. All raw materials purchases are on credit, and no payables arise from any other transactions. One months raw materials purchases are fully paid in the next month.
  10. The minimum ending cash balance for all months is $45,000. If necessary, the company borrows enough cash using a short-term note to reach the minimum. Short-term notes require an interest payment of 1% at each month-end (before any repayment). If the ending cash balance exceeds the minimum, the excess will be applied to repaying the short-term notes payable balance.
  11. Dividends of $15,000 are to be declared and paid in May.
  12. No cash payments for income taxes are to be made during the second calendar quarter. Income tax will be assessed at 35% in the quarter and paid in the third calendar quarter.
  13. Equipment purchases of $135,000 are budgeted for the last day of June.

Required: Prepare the following budgets and other financial information as required. All budgets and other financial information should be prepared for the second calendar quarter, except as otherwise noted below. (Round calculations up to the nearest whole dollar, except for the amount of cash sales, which should be rounded down to the nearest whole dollar.): 1. Sales budget. 2. Production budget. 3. Raw materials budget. 4. Direct labor budget. 5. Factory overhead budget. 6. Selling expense budget. 7. General and administrative expense budget. 8. Cash budget. 9. Budgeted income statement for the entire second quarter (not for each month separately). 10. Budgeted balance sheet.

ZIGBY MANUFACTURING
Sales Budget
April, May, and June 2017
Budgeted Unit Sales Budgeted Unit Price Budgeted Sales Dollars
April 2017
May 2017
June 2017
Totals for the second quarter

ZIGBY MANUFACTURING
Production Budget
April, May, and June 2017
April May June
Next month's budgeted sales (units) 19,000 19,500 20,000
Ratio of inventory to future sales 80% 80% 80%
Required units of available production
Units to be produced
ZIGBY MANUFACTURING
Raw Materials Budget
April, May, and June 2017
April May June
Production budget (units)
Materials needed for production
Total materials requirements (units)
Materials to be purchased
Material price per unit
Budgeted raw material purchases
ZIGBY MANUFACTURING
Direct Labor Budget
April, May, and June 2017
April May June Total
Budgeted production (units)
Total labor hours needed
Budgeted direct labor cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

What has been your desire for leadership in CVS Health?

Answered: 1 week ago

Question

Question 5) Let n = N and Y Answered: 1 week ago

Answered: 1 week ago