Problem 8-18A Comprehensive Variance Analysis [LO8-4, LO8-5, LO8-6] Miller Toy Company manufactures a plastic swimming pool at its Westwood Plant. The plant has been experiencing

Problem 8-18A Comprehensive Variance Analysis [LO8-4, LO8-5, LO8-6]

Miller Toy Company manufactures a plastic swimming pool at its Westwood Plant. The plant has been experiencing problems as shown by its June contribution format income statement below:

Budgeted Actual
Sales (3,000 pools) $ 210,000 $ 210,000
Variable expenses:
Variable cost of goods sold* 38,220 49,235
Variable selling expenses 15,000 15,000
Total variable expenses 53,220 64,235
Contribution margin 156,780 145,765
Fixed expenses:
Manufacturing overhead 66,000 66,000
Selling and administrative 81,000 81,000
Total fixed expenses 147,000 147,000
Net operating income (loss) $ 9,780 $ (1,235)
*Contains direct materials, direct labor, and variable manufacturing overhead.

Janet Dunn, who has just been appointed general manager of the Westwood Plant, has been given instructions to get things under control. Upon reviewing the plants income statement, Ms. Dunn has concluded that the major problem lies in the variable cost of goods sold. She has been provided with the following standard cost per swimming pool:

Standard Quantity or Hours Standard Price or Rate Standard Cost
Direct materials 3.1 pounds $ 2.60 per pound $ 8.06
Direct labor 0.5 hours $ 7.20 per hour 3.60
Variable manufacturing overhead 0.4 hours* $ 2.70 per hour 1.08
Total standard cost $ 12.74
*Based on machine-hours.

During June the plant produced 3,000 pools and incurred the following costs:
a.

Purchased 14,300 pounds of materials at a cost of $3.05 per pound.

b.

Used 9,100 pounds of materials in production. (Finished goods and work in process inventories are insignificant and can be ignored.)

c. Worked 2,100 direct labor-hours at a cost of $6.90 per hour.
d.

Incurred variable manufacturing overhead cost totaling $4,650 for the month. A total of 1,500 machine-hours was recorded.

It is the companys policy to close all variances to cost of goods sold on a monthly basis.

Required:
1. Compute the following variances for June:

a.

Materials price and quantity variances. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).)

b.

Labor rate and efficiency variances. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).)

c.

Variable overhead rate and efficiency variances. (Do not round your intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).)

2.

Summarize the variances that you computed in (1) above by showing the net overall favorable or unfavorable variance for the month. (Input all values as positive amounts. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).)

3.

Pick out the two most significant variances that you computed in (1) above. (You may select more than one answer. Single click the box with a check mark for correct answers and double click to empty the box for the wrong answers.)

Materials price variance
Labor efficiency variance
Variable overhead efficiency variance
Labor rate variance
Variable overhead rate variance
Materials quantity variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Next Step Advanced Medical Coding And Auditing 2016

Authors: Carol J. Buck MS CPC CCS-P

1st Edition

978-0323389105

More Books

Students also viewed these Accounting questions

Question

=+ (e) The probability in Problem 2.15.

Answered: 1 week ago

Question

SS O 0.999 QUESTION 7 P (z

Answered: 1 week ago

Question

What aspects would it be impossible to capture?

Answered: 1 week ago

Question

Enhance your words with effective presentation aids

Answered: 1 week ago