PROCESS BURST TIME PRIORITY P1 125 3 P2 62 1 P3 45 2 P4 113 4 Using the following chart, create a Gantt Chart for
PROCESS | BURST TIME | PRIORITY |
P1 | 125 | 3 |
P2 | 62 | 1 |
P3 | 45 | 2 |
P4 | 113 | 4 |
Using the following chart, create a Gantt Chart for a non-preemptive priority where the lowest number is the highest priority and another for SJF. Then calculate the average throughput and turnaround time for each one.