Process P 1 P 2 Burst Time 2 4 3 P 3 3 Draw the Gantt chart and calculate average waiting time and turnaround time
Process
P
P
Burst Time
P
Draw the Gantt chart and calculate average waiting time and turnaround time for the following snapshot of process using FCFS scheduling algorithm.