1 Approved Answer

Product A is an end item and is made from two units of B, three units of C and three units of D. B is

  1. Product A is an end item and is made from two units of B, three units of C and three units of D. B is made of three units of E and two of F. C is made of two units of F and one of D. A and B have a lead time of one week. C and D have lead times of two weeks, and E and F have lead times of three weeks. Lot sizes for A, B and D are L4L. Item C has a lot size of 50. E and F have a lot size of 100. There is 50 units of item B on hand, and 10 units of item A. There is a scheduled receipt for 50 units of item F in week three.
  2. Show the bill of materials (product structure tree)
  3. If 150 units of A are required in Week 8, develop the MRP planning schedule, specifying when items are to be ordered and received.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foodservice Management Principles And Practices

Authors: June Payne Palacio, Monica Theis

13th Edition

0133801101, 9780133801101

More Books

Students also viewed these General Management questions

Question

Econometric methodologies in testing the CAPM

Answered: 1 week ago