Product A is an end item and is made from two units of B and four of C . B is made of two units
Product is an end item and is made from two units of and four of is made of two units of and two of is made of two units of and two of
A has a lead time of one week. B C and have lead times of two weeks, and and have lead times of three weeks.
b If units of A are required in Week develop the MRP planning schedule, specifying when items are to be ordered and received. There are currently no units of inventory on hand. Leave no cells blank be certain to enter wherever required.