Product XX Customer need 6 0 0 pcs / week Orders 3 5 0 and 2 5 0 pcs twice a week Material flow Production

Product XX
Customer need 600 pcs/week
Orders 350 and 250 pcs twice a week
Material flow
Production in 3 phases
Operation A
Cycle time 60 seconds
Setup time 4 hours
Uptime 80%
Available 4 hours/day
Operation B
Cycle time 360 seconds
Setup time 10 minutes
Uptime 80%
Available 7 hours/day
Quality 95%
Operation C
Cycle time 180 seconds
Setup time 30 minutes
Uptime 90%
Available 7 hours/day
Production schedule to production phases
Digital, once a week
Inventories (after each operation)
Coils 1680 pcs
Operation A 1380 pcs
Operation B 480 pcs
Operation C 924 pcs
Shipping
Twice a week, 350 and 250 pcs
Tuesday and Friday
Material delivery
Order and delivery 1300 pcs fortnightly on any day during a
week draw a value stream map for this product. Nanufacturing systemsvdevelopment
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books

Students also viewed these General Management questions