Question
Production - 75,000 units Raw Material - 270,000 pounds at a cost of $1,026,000 Direct Labor - 187,500 hours at a cost of $4,125,000 Variable
Production - 75,000 units
Raw Material - 270,000 pounds at a cost of $1,026,000
Direct Labor - 187,500 hours at a cost of $4,125,000
Variable Overhead - 135,000 machine hours at a cost of $567,000
Fixed Overhead - $900,000
At the end of year, the actual results were as follows -
Production - 73,000 units
Raw Material - 265,720 pounds purchased and used at a cost of $1,036,308
Direct Labor - 179,580 hours at a cost of $3,968,718
Variable Overhead - 133,590 machine hours at a cost of $558,406.20
Fixed Overhead - $891,000
1) What is the raw material standard for the amount of pounds per unit ?
2) What is the standard price per pound of raw material ?
3) What is the Raw Material Efficiency Variance ?
4) What is the Raw Material Price Variance ?
5) What is the Direct Labor standard for hours per unit?
6) What is the standard price per Direct Labor hour ?
7) What is the Direct Labor Efficiency Variance?
8) What is the Direct Labor Rate Variance?
9) What is the Total Variance for Direct Labor ?
10) What is the standard rate per machine hour for Variable Overhead ?
11) What is the Efficiency Variance for Variable Overhead ?
12) What is the Variable Overhead Rate Variance ?
13) What is the Total Variance for Variable Overhead ?
14) What is the standard for Fixed Overhead per unit ?
15) What is the Volume-Variance for Fixed Overhead ?
16) What is the Spending Variance for Fixed Overhead ?
17) What is the Total Variance for Fixed Overhead ?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started