production planning 21) Material requirement planning system is suitable: a) In case of unpredictable and fluctuating demand b) In case of a very stable demand
production planning
21) Material requirement planning system is suitable: a) In case of unpredictable and fluctuating demand b) In case of a very stable demand with low variety in products In case of highly predictable and reliable demand In all previous cases None Step by Step Solution