Profit-Linked Productivity Measurement In 20x2, Choctaw Company implements a new process affecting labor and materials. Choctaw Company provides the following information so that total productivity
Profit-Linked Productivity Measurement
In 20x2, Choctaw Company implements a new process affecting labor and materials.
Choctaw Company provides the following information so that total productivity can be valued:
20x1 | 20x2 | |
Number of units produced | 540,000 | 450,000 |
Labor hours used | 180,000 | 225,000 |
Materials used (lbs.) | 2,700,000 | 1,500,000 |
Unit selling price | $20 | $22 |
Wages per labor hour | $14 | $16 |
Cost per pound of material | $3.40 | $3.50 |
Required:
1. Calculate the cost of inputs in 20x2, assuming no productivity change from 20x1 to 20x2. If required, round your answers to the nearest dollar.
Cost of labor | $ |
Cost of materials | |
Total PQ cost | $ |
2. Calculate the actual cost of inputs for 20x2. If required, round your answers to the nearest dollar.
Cost of labor | $ |
Cost of materials | |
Total current cost | $ |
What is the net value of the productivity changes? If required, round your answers to the nearest dollar. $
How much profit change is attributable to each input's productivity change? If an item is negative, use a minus (-) sign to indicate.
Labor productivity change | $ |
Materials productivity change | $ |
3. What if a manager wants to know how much of the total profit change from 20x1 to 20x2 is attributable to price recovery? Calculate the total profit change. $
Calculate the price-recovery component. $
MY RESULTS SO FAR...
1,800,000 X 7,650,000 X 9,450,000 X Cost of labor Cost of materials Total PQ cost 2. Calculate the actual cost of inputs for 20x2. If required, round your answers to the nearest dollar Cost of labor Cost of materials Total current cost What is the net value of the productivity changes? If required, round your answers to the nearest dollar. 3,600,000 5,250,000 8,850,000 How much profit change is attributable to each input's productivity change? If an item is negative, use a minus (-) sign to indicate Labor productivity change Materials productivity change 3. What if a manager wants to know how much of the total profit change from 20x1 to 20x2 is attributable to price recovery? Calculate the total profit change -1,200,000 -4,462,500 X -450,000X Calculate the price-recovery component. 150,000 X Next Previous Check My Work 0 more Check My Work uses remaining. 1,800,000 X 7,650,000 X 9,450,000 X Cost of labor Cost of materials Total PQ cost 2. Calculate the actual cost of inputs for 20x2. If required, round your answers to the nearest dollar Cost of labor Cost of materials Total current cost What is the net value of the productivity changes? If required, round your answers to the nearest dollar. 3,600,000 5,250,000 8,850,000 How much profit change is attributable to each input's productivity change? If an item is negative, use a minus (-) sign to indicate Labor productivity change Materials productivity change 3. What if a manager wants to know how much of the total profit change from 20x1 to 20x2 is attributable to price recovery? Calculate the total profit change -1,200,000 -4,462,500 X -450,000X Calculate the price-recovery component. 150,000 X Next Previous Check My Work 0 more Check My Work uses remainingStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started