Question

1 Approved Answer

Project 2 - 6 : Correcting Errors in a Project Schedule A student who is interning with your company made some updates to the music

Project 2-6: Correcting Errors in a Project Schedule
A student who is interning with your company made some updates to the music video project schedule. Unfortunately, he is still learning about Microsoft Project and has entered some information incorrectly. In this
project, you will correct the problems with the project schedule before distributing it to your team.
ONLINE
The Remote Drone Incorrect 2-6 project schedule is available on the book companion website.
GET READY. OPEN Remote Drone Incorrect 2-6 from the data files for this lesson.
Review the Resource Sheet for this project schedule.
Based on what you have learned in this lesson about resource types, maximum units, and standard rates, find the resource errors in this project schedule and make corrections to them. (Hint. There are three
resource errors in the project schedule.)
Study the last three resources on the sheet. For example, if pens is actually a work resource and bottled water is actually a cost resource, make corrections to the information given for these three resources
(estimate the rate if necessary).
SAVE the project schedule as Remote Drone Corrected Resources and then CLOSE the file.
CLOSE Project. Jan 13,'19
jJan 20,'19
Jan 27,'19
jFeb 3,'19
Feb 10,'19
Feb 17,'19
|Mar 3,
Feb 24,'19
Add tasks with dates to the timeline
Mon 1/7/19
q, Start q,
q,
q,Jamie Reding Work J 100% $1,500.00/wk $0.00/hr $0.00 Prorated Standard
Scott Seely Work S 100% $22.50/hr $0.00/hr $0.00 Prorated Standard
Jeff Pike Work J 100% $1,000.00/wk $0.00/hr $0.00 Prorated Standard
Judy Lew Work J 100% $29.50/hr $0.00/hr $0.00 Prorated Standard
Brenda Diaz Work B 100% $19.75/hr $0.00/hr $0.00 Prorated Standard
Brad Sutton Work B 100% $16.50/hr $0.00/hr $0.00 Prorated Standard
Annette Hill Work A 50% $20.00/hr $0.00/hr $0.00 Prorated Standard
Ryan Ihrig Work R 100% $16.00/hr $0.00/hr $0.00 Prorated Standard
Yan Li Work Y 100% $28.50/hr $0.00/hr $0.00 Prorated Standard
Model technician Work M 200% $16.50/hr $0.00/hr $0.00 Prorated Standard
Digital camera Work D 200% $300.00/wk $0.00/hr $0.00 Prorated Standard
Anemometer Work A 100% $20.00/wk $0.00/hr $0.00 Prorated Standard
Safety tether Work S 100% $5.00/wk $0.00/hr $0.00 Prorated Standard
Clipboards Work C 800% $0.00/hr $0.00/hr $0.00 Prorated Standard
Large Conference Room Work L 100% $0.00/hr $0.00/hr $0.00 Prorated Standard
Small Conference Room Work S 300% $0.00/hr $0.00/hr $0.00 Prorated Standard
SD Card Material 4 GB S $0.00 $0.00 Prorated
Printer paper Material Ream P $0.00 $0.00 Prorated
Travel Cost T Prorated
Food Cost F Prorated
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Promoting Your Firearms Training Business

Authors: Jay Tiffin

1st Edition

979-8460283323

More Books

Students also viewed these Finance questions