Project #2 Percentage of Completion During 2019, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2021.
Project #2 Percentage of Completion
During 2019, Martinez Company started a construction job with a contract price of $1,580,000. The job was completed in 2021. The following information is available.
2019 | 2020 | 2021 | ||||
Costs incurred to date | $404,000 | $853,160 | $1,073,000 | |||
Estimated costs to complete | 606,000 | 254,840 | 0 | |||
Billings to date | 301,000 | 904,000 | 1,580,000 | |||
Collections to date | 271,000 | 812,000 | 1,418,000 |
Instructions:
- Complete a chart analyzing the above information showing revenue, the % of completion every year and the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
- Prepare all necessary journal entries for 2019, 2020, and 2021.
- Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started