Project A has a NPV(A) = $5280, Project B has a NPV(B) = $8200, and Project C has a NPV(C) = -$1500. If these are
Project A has a NPV(A) = $5280, Project B has a NPV(B) = $8200, and Project C has a NPV(C) = -$1500. If these are independent projects then,
a. you should accept only Project A
b. you should accept only Project B
c. you should accept both Project A and Project B
d. you should accept all three projects (A, B, and C) since the sum total of all three NPVs is positive